Project Overview

Provided site work for new student housing on University of Delaware campus.

  • Cut/Fill 24,000 CY
  • Cut/Haul 11,500 CY
  • Import 10,000 CY
  • Machine Grading 54,000 SY
  • Sanitary Sewer 3,200 LF
  • Storm Sewer 5,100 LF
  • Roof Drains 1,000 LF
  • 3 Storm Techs
  • 3,000 CY excavated for 3 Bio Ponds
  • 9,500 LF Waterline
  • 10,000 LF Curb
  • 5,000 TON Hot Mix Asphalt
  • 4,935 SY Sidewalk

Key Challenges

  • Corrado Construction Company worked alongside several subcontractors in a congested area.
  • The housing campus was split into two sides by a shopping center.
  • Our scope doubled but the schedule remained the same.
  • We worked extended hours to meet the schedule.

PROJECT DETAILS

Project:The Retreat at Newark

Client:Collegiate Construction LLC

Location:Newark, DE

Classification:Residential

Job Size:$3 - $5 Million

Duration:1 Year

Date of CompletionSeptember 2014

PORTFOLIO