Project Overview

This two-acre project, which sits on the previous location of Leon’s Garden Center in North Wilmington, included erosion controls, earthwork, sanitary sewer, storm pipe, water line, bio-retention basins, concrete and asphalt paving. The job also required two DelDOT entrances servicing Rt 202 and Rocky Run Parkway.

  • Earthwork: 6,000 CY
  • Storm sewer: 700 LF
  • Sanitary sewer: 7800 LF
  • Waterline: 500 LF
  • Sidewalk: 2,500 SF
  • Curb: 1,200 LF
  • Paving: 400 tons

Key Challenges

Due to the limited space available on the site, Corrado Construction worked with the client to get the bio-retention basins completed prior to starting the building construction, with our crews working through the winter season to keep the project on schedule.

PROJECT DETAILS

Project:WSFS Bank at Rocky Run

Client:DSM Construction

Design Professional:Duffield Associates

Location:Wilmington, DE

Classification:Commercial

Job Size:$1 - $3 Million

Duration:8 Months

Date of CompletionJune 2017