Project Scope

Full site work package including:

  • Building pad preparation for hotel
  • Site utilities including storm sewer, sanitary sewer, water line, and roof drains
  • Full install of a 3,817 SF Rain Tank
  • Curb, Stone, and site paving

Key Challenges

Supply chain issues greatly affected the ability to procure the rain tank material in a timely fashion. CCC worked with the GC to adjust the install schedule.

Project:Fairfield Inn

Client:Lighthouse Construction

Design Professional:C Bahksh

Location:Middletown, DE

Job Size:Under 1 Million

Duration:15 Months

Date of Completion:July 2022