• Skip to primary navigation
  • Skip to main content

Corrado Construction Company

Merit shop site development contractor serving DE, MD, PA, NJ

  • Home
  • About
  • Services
  • Safety
  • Portfolio
  • News
  • Careers
  • Contact
  • Show Search
Hide Search

Lowes

Commercial

ProjectLowes
ClientBancroft Construction
Design Professional
LocationNew Castle, DE
Job Size3 – 5 Million
Duration5 months
Date of CompletionDecember 2015

Project Overview

Site construction of a fourteen acre parcel from a Greenfield to a commercial building site. The site work also included two major upgrades to DelDOT infrastructure: completing a 2,000 LF roadway and increasing the length of an existing turn lane on Rt. 7 by 350 LF.

  • 70,500 CY of Cuts/Fills
  • 19,500 CY of Imported Fill
  • 23,000 Tons of Stone
  • 550 LF of Sanitary Sewer
  • 3,400 LF of Storm Drain
  • 1,500 LF of Rainwater
  • 2,200 LF of Waterline
  • 3 Bio Ponds were installed totaling 3,900 SF of bio pond
  • 13,000 SF of Sidewalks
  • 5,300 SF of Heavy Duty Concrete Paving
  • 6,500 Tons of Hot Mix Asphalt

Key Challenges

This project had a short timeline for completion – less then six weeks. All work was completed in order for Lowe’s to open on time in the first quarter of 2015.
The site needed over 25,000 CY of unanticipated import due to undercut and much thicker topsoil than anticipated.
Lowe’s building contractor worked at a fast pace, requiring coordination of work from pre-construction through final completion.
The stormwater management areas that were planned to be infiltration basins did not support vegetative growth. We worked with the county to provide an acceptable alternative (sand-lined ponds) in order to achieve stabilization and infiltration.
Much of the finish work (landscaping, paving, concrete etc.) was performed in November and December. We were able to meet Lowe’s and DelDOT’s specifications for temperatures because we were two weeks ahead of schedule entering the winter. If we were “on schedule” we would have been hit by multiple snow storms – delaying the opening of the Lowe’s by months.

Published on:
December 10, 2015

Explore more

Join the Crew Portfolio

Footer

Two Locations in Delaware

New Castle
210 Marsh Lane
New Castle, DE 19720
302-652-3339

__

Millsboro
29864 Millsboro Highway
Millsboro, DE 19966

Copyright © 2025 · Corrado Construction Company · Log in

Get Connected